Operation and Maintenance of Potable Water Supply System

  • All well transmission lines, distribution mains (350,000 lineal feet), service laterals and meter assemblies (199 active connections)
  • 4 Water Tanks (2 million gallons storage), 5 Booster Stations, 2 Transfer Stations 
  • 22 Pressure Zones [28 Pressure Reducing Stations (56 valves)]
  • 36 wells connected to potable system
  • 5 primary water treatment facilities and several local treatment systems
  • Supervisory Control and Data Acquisition (SCADA) network (remote monitoring and control system)
  • Growth, maintenance, and security of SCADA network (software, hardware, programming, integration)
  • 230+ fire hydrants 
  • GIS data collection, growing and maintaining accurate mapping of system assets

Operation and Maintenance of Irrigation Well Water Supply System

  • Water storage & transfer, water loss management, and pond system maintenance
  • Maintenance & repairs of 4 transfer pumps and motors
  • Maintenance & repairs of SCADA equipment
  • Supply lines connected only to the golf course irrigation pond system
  • 29 active wells connected to golf irrigation system

Operation and Maintenance at Moore's Lake

  • Responsible for Moore's Lake water right permit compliance
  • Daily lake level, Garzas Creek flow data recording, and flow adjustments
  • Operate and maintain siphons and sluice gate at dam
  • 16-ring aeration system at Moore’s Lake

Residential Water Rates - Monthly

(Rates per 1000 gallons)

$2.04 1st 5000
$4.08 next 5000
$6.12 next 5000
$8.16 next 5000
$16.33 Thereafter

 

Construction Phase Water Rates - Monthly

(Rates per 1000 gallons)

$2.04 1st 5000
$4.08 next 5000
$6.12 next 5000
$8.16 Thereafter